Purok 1 · Estrella
Estrella canal desilting
Desilt 180 meters of the Estrella canal, rebuild two headwalls, and keep the pump staged at the covered court through the monsoon.
- Fund
- 20% development fund
- Lead
- Kagawad Jackson T. Lopez
Budget used
₱420,000 of ₱680,000
62% used
Remaining ₱260,000
Updates
1 September 2026
Second reach opened
Crews reached the bend by the Estrella marker. Silt is stacked for hauling on Thursday. Residents on the second step should keep appliances up until Friday's tide.
18 August 2026
Pump and first 80 meters
The hall pump is in place. First eighty meters cleared. One headwall poured.
4 August 2026
Notice to proceed
Contractor mobilized. Work window is 7:00 a.m. to 3:00 p.m., Monday to Saturday, to miss high tide.