All projects
Purok 6 drainage run
Procurement

Purok 6 · Covered court

Purok 6 drainage run

New lined drain from the court to the canal so rain does not sit on the street until afternoon.

Fund
20% development fund
Lead
Kagawad Jackson T. Lopez

Budget used

₱45,000 of ₱390,000

12% used

Remaining ₱345,000

Updates

  1. 26 August 2026

    Bids under evaluation

    Three quotations opened at the hall. Award expected in the second week of September. Survey stakes are up — do not move them.

  2. 8 August 2026

    Survey complete

    Levels taken from the court apron to the canal wall. Mobilization paid.